Skip to main content
Pacific Rim Dairy | California

Case Study

Pacific Rim Dairy | California

Three-lagoon, two-stage digestion system at Pacific Rim Dairy in California, repurposing existing ponds with HDPE covers and air injection.

Historical project details checked against the original EFI case history on September 16, 2026. Reported equipment and operating results describe that project period.

3x lagoons at approx. 98ft x 660ft each
Lagoon Dimensions
HDPE
Material
Client
Pacific Rim Dairy
Location
California
Completed
2014
Industry
Dairy
System Type
Covered Lagoon Digester with Biogas Collection

The Challenge

Problem

Pacific Rim Dairy sought to use three existing manure lagoons for anaerobic digestion. Maas Energy Works developed the project, with process design by Dr. Hector Cumba and civil design by 4-Creeks Inc.

Our Approach

Solution

The 2014 case history describes a two-stage process across three lagoons. EFI installed baffle and mixing systems, HDPE covers and air injection for biogas conditioning.

Floating CoverBiogas SystemBaffle SystemMixer SystemO2 Injection

Historical record

Documented Scope

3x lagoons at approx. 98ft x 660ft each
Lagoon Dimensions
HDPE
Material

Project Details

  • Three existing lagoons incorporated in the design
  • Baffle and mixing systems installed